Change fields in the Task Progress area of My Work RRS feed

  • Question

  • I am trying to change the Timephased Work field to a Completed Work field on the Details page of My Work in PWA 2010.

    I can change the fields in the lower, Task Properties section of the page by going to the "Manage Views" secton of server settings and going to the "My Work", "Details" section, but there is now way to change the Total Work and Timephased Work columns in the Task Progress area (see picture).

    Can someone show me how I can change the fields in the Task Progress area?

    Thank you


    Daren Johnson
    Thursday, November 17, 2011 7:52 PM

Answers

  • Dale,

    We figured out how to change the task progress fields.  The setting is via the "Task Settings and Display" on the Server Settings page:

    When the Timephased field was showing the "Tracking Method" was set to "Hours of work done per period".  When we changed it to "Actual work done and work remaining", it changed the "Timephased work" field to "Completed work"

    Someone within our group had inadvertently unchecked the box in the Project Web App Permissions under the security group to not allow administrators the ability to see all of the available options under Time and Task Management.  Someone with farm admin permissions was able to track down the fix for us.

    Thanks!


    Daren Johnson
    Monday, November 21, 2011 7:16 PM

All replies

  • Daren --

    I do not believe there is any way to change those fields.  Sorry.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, November 17, 2011 8:25 PM
    Moderator
  • Well Dale, I thought the same thing... then I noticed on another installation we have of PWA that the fields are different.  Don't know how they got the way they did cause I have been searching for a way to change them for weeks.


    Daren Johnson
    Thursday, November 17, 2011 9:16 PM
  • Daren --

    No idea.  Sorry.  Maybe someone else in this forum has an idea for you.

    "DarenJ" wrote in message news:fb9ba8c7-0569-4e4e-9c3f-bc28b0c66367@communitybridge.codeplex.com...

    Well Dale, I thought the same thing... then I noticed on another installation we have of PWA that the fields are different.  Don't know how they got the way they did cause I have been searching for a way to change them for weeks.

    <http://social.microsoft.com/Forums/getfile/34868/>


    Daren Johnson


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Thursday, November 17, 2011 9:37 PM
    Moderator
  • Dale,

    We figured out how to change the task progress fields.  The setting is via the "Task Settings and Display" on the Server Settings page:

    When the Timephased field was showing the "Tracking Method" was set to "Hours of work done per period".  When we changed it to "Actual work done and work remaining", it changed the "Timephased work" field to "Completed work"

    Someone within our group had inadvertently unchecked the box in the Project Web App Permissions under the security group to not allow administrators the ability to see all of the available options under Time and Task Management.  Someone with farm admin permissions was able to track down the fix for us.

    Thanks!


    Daren Johnson
    Monday, November 21, 2011 7:16 PM
  • Darren --

    Congrats to you, my friend, for finding the solution to your own problem! :)  And you are more than welcome for the help as well.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Monday, November 21, 2011 9:18 PM