Physical % Complete in Global RRS feed

  • Question

  • Hello all,

    Is there a way to setup Global.MPT to set earned value method to be Physical % Complete? Such that if the Global is saved and used among different people / projects that they would by default use Physical % Complete? 

    Similarly, is there a means to saving resources on the Global Physical % Complete so that they are available to all that share that global?

    Thanks!


    Monday, March 26, 2012 10:00 PM

Answers

  • you can set Physical % complete in Project for all new projects (not retroactively for existing protects: do them manually). Your IS team can then copy your Global.mpt file to ll PMs. I also recommend setting up some default Views, tables and filters as well before doing this.

    You can't save resources in the Global file. Instead you either need a resource pool or a template blank project with resources in.


    Rod Gill

    The one and only Project VBA Book Rod Gill Project Management

    Tuesday, March 27, 2012 12:18 AM