Risks List Trigger Date RRS feed

Answers

  • Hi Noman,

    The trigger in the risk form proposes a list of possible triggers which will make the risk to happen. If you select "date", this is actually just to mention that your risk will occur if something goes after a certain date. Another choice "task not completed" means that the risk will occur if you don't complete a task. The objective is not to enter the given date but to give the information about the risk trigger.

    So it is not related in any way to the due date which corresponds to the date the risk should be solved.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Thursday, March 10, 2016 10:23 AM
    Moderator

All replies

  • Hi Noman,

    The trigger in the risk form proposes a list of possible triggers which will make the risk to happen. If you select "date", this is actually just to mention that your risk will occur if something goes after a certain date. Another choice "task not completed" means that the risk will occur if you don't complete a task. The objective is not to enter the given date but to give the information about the risk trigger.

    So it is not related in any way to the due date which corresponds to the date the risk should be solved.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Thursday, March 10, 2016 10:23 AM
    Moderator
  • Great - Thanks Guillaume!

    Noman Sohail

    Thursday, March 10, 2016 12:30 PM