report of pending approvals by status manager RRS feed

  • Question

  • The Project Server Admin needs to know who many tasks and under which project does a project manager/status manager have pending tasks from approval.

    For eg:

    we take a report every month of all the resources hours on projects, but in some cases the PM forgets to approve and thus the hours are not reflected in the report.

    Is there a way where the EPM admin can run a report and see which PM has not approved some actuals and thus take some action on informing him/her before producing the actuals report for the month?

    Tuesday, May 7, 2013 10:39 AM

All replies

  • Sameer,

    You have not told us which version of project Server you are using. 

    There used to be a report in the EPM Report Pack that ws released for 2007 version, called the Task update Compliance Report, which gives what you need.

    You should be able to get it working for Project Server 2010 with some tweaks.

    http://archive.msdn.microsoft.com/EPMReportPack

    Here is a screenshot of the report:


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    Wednesday, May 8, 2013 12:48 PM