    Your question leaves lots of room for interpretation and follow up questions.  For example, will all of the people do work on every task?  When you assign each resource to every task, will each resource be working full-time or part-time on each task?  Will they be working full-time on some tasks and part time on others?
     
    Let�??s assume that each resource will work full-time on every task.  I would recommend you follow this process:
    1. Select a block of regular tasks (DO NOT select any summary tasks).
    2. Display the Assign Resources dialog.
    3. Select all of the resources in the dialog and then click the Assign button.
    4. Continue selecting blocks of regular tasks and then repeat step #3 until you have assigned the resources to every task in the project.
    By the way, you have erroneously posted this question in a user forum dedicated only to questions about Project Online.  I would recommend in the future that you post your Microsoft Project 2003 desktop questions in the Project Standard and Professional General Questions and Answers forum instead.  Hope this helps.
     

    Dale A. Howard [MVP]

    Thursday, June 6, 2013 7:47 PM
    Moderator