  • Hello can you please help me. In my project plan tasks planned for future have the "Late" status. What is the reason for this?
    Wednesday, April 13, 2016 5:25 PM

All replies

  • Can you post a screenshot or even send the file (contact me with LinkedIn)?

    Can you check the status date in the project tab of the ribbon? The status is calculated based on this status date.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Wednesday, April 13, 2016 6:10 PM
    Moderator
  • Do they finish in the future or they start in  the future?
    Thursday, April 14, 2016 8:06 AM
  • If the task finishes in the future but the progress is up to the status date, it will be on schedule (task D). But if it finishes in the future but the progress is not as expected (task A), then it will be late.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Thursday, April 14, 2016 8:52 AM