Saturday and Sunday as working days RRS feed

  • Question

  • We are doing a civil project. we need to identify all saturdays and sundays as working days. Please help us in converting these two days also as working days. 

    warm regards

    Tuesday, September 5, 2017 9:44 AM

All replies

  • Dr. Ravikumar,

    It's pretty straightforward, just follow these steps.

    1. Go to Project > Properties group > Change Working time

    2. Hit the button to Create New Calendar

    3. Assuming you simply want to add Saturday and Sunday to the Standard calendar, just give your new calendar a name (e.g. 7 day week)

    4. Hit the Work Weeks tab at the bottom of the Change working time window, then hit "Details"

    5. Sunday should be selected by default so select the "Set day(s) to these specific working times" and enter the "from" and "to" work shifts

    6. Repeat step 5 for Saturday

    Once you have the new calendar go to Project > Project Information and in the "Calendar" selection box, find your new custom calendar and select it

    That should do it unless you need to have specific tasks and/or resources follow a different calendar.

    Hope this helps.

    John