WBS Renumber Not Working RRS feed

  • Question

  • Project 2010...will not allow WBS renumber when trying to choose "Selected tasks" and does not renumber when select entire project.
    Monday, April 22, 2013 4:49 PM

All replies

  • When choosing Selected Tasks, you have to select a set of tasks that will allow Project to renumber them.

    I find that Entire Project doesn't work.  So I do this:  Select all tasks.  Then renumber Selected Tasks.


    Reid McTaggart – DeltaBahn Vice President