  • Hi,

    Is it possible to display several, 3 or 4, milestones on the Gantt bars of the Summary view of Project Center 2013?

    For every projects of course.

    Thanks for any idea

    Tuesday, April 26, 2016 5:52 PM

Answers

  • Hi Guillaume,

    I did that in Project Server 2010. It's probably the same for 2013.

    Have a look at my FAQ #57:

    http://www.pragma-soft.com/faq2010/faq.htm?lien=57.htm

    Thanks and regards


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    Friday, April 29, 2016 4:26 PM

All replies

  • Hi,

    The short answer is no, you cannot rollup milestones in the project center views.

    That being said, you have (at least) 2 workarounds:

    • Display milestones as a column in the left part of the project center: http://aboutmsproject.com/how-to-show-implementation-milestone-dates-in-project-center/
    • Show bar styles instead of milestones: http://www.theprojectcornerblog.com/2015/04/08/build-custom-bar-styles-in-project-center-using-project-server-and-project-online/

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Wednesday, April 27, 2016 6:14 AM
    Moderator
  • Hi Guillaume,

    I did that in Project Server 2010. It's probably the same for 2013.

    Have a look at my FAQ #57:

    http://www.pragma-soft.com/faq2010/faq.htm?lien=57.htm

    Thanks and regards


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    Friday, April 29, 2016 4:26 PM
  • Good to know Gérard! I've see this request many times without figuring it out! Thanks for the tip!

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    Saturday, April 30, 2016 6:56 AM