Project 2013 hangs after click "Change working time" with manually edited xml RRS feed

  • Question

  • I have edited xml, added to tasks 2 and 3 this fields:

    <ActualWork>PT117H36M0S</ActualWork><ActualDuration>PT117H36M0S</ActualDuration><RemainingWork>PT274H24M0S</RemainingWork><RemainingDuration>PT274H24M0S</RemainingDuration><ActualStart>2016-01-12T08:00:00</ActualStart><PercentWorkComplete>30</PercentWorkComplete><PercentComplete>30</PercentComplete>

    Result xml is

    <?xml version="1.0" encoding="utf-8" standalone="yes"?>
    <Project xmlns="http://schemas.microsoft.com/project">
      <SaveVersion>14</SaveVersion>
      <Name>First Project.xml</Name>
      <Title>First Project</Title>
      <Company>E</Company>
      <Author>The</Author>
      <CreationDate>2016-02-02T00:00:00</CreationDate>
      <LastSaved>2016-02-02T00:00:00</LastSaved>
      <ScheduleFromStart>1</ScheduleFromStart>
      <StartDate>2016-01-12T00:00:00</StartDate>
      <FinishDate>2016-02-29T00:00:00</FinishDate>
      <FYStartDate>1</FYStartDate>
      <CriticalSlackLimit>0</CriticalSlackLimit>
      <CurrencyDigits>2</CurrencyDigits>
      <CurrencySymbol>�</CurrencySymbol>
      <CurrencyCode>EUR</CurrencyCode>
      <CurrencySymbolPosition>0</CurrencySymbolPosition>
      <CalendarUID>1</CalendarUID>
      <DefaultStartTime>08:00:00</DefaultStartTime>
      <DefaultFinishTime>17:00:00</DefaultFinishTime>
      <MinutesPerDay>480</MinutesPerDay>
      <MinutesPerWeek>10080</MinutesPerWeek>
      <DaysPerMonth>30</DaysPerMonth>
      <DefaultTaskType>0</DefaultTaskType>
      <DefaultFixedCostAccrual>3</DefaultFixedCostAccrual>
      <DefaultStandardRate>0</DefaultStandardRate>
      <DefaultOvertimeRate>0</DefaultOvertimeRate>
      <DurationFormat>7</DurationFormat>
      <WorkFormat>1</WorkFormat>
      <EditableActualCosts>0</EditableActualCosts>
      <HonorConstraints>0</HonorConstraints>
      <InsertedProjectsLikeSummary>1</InsertedProjectsLikeSummary>
      <MultipleCriticalPaths>0</MultipleCriticalPaths>
      <NewTasksEffortDriven>0</NewTasksEffortDriven>
      <NewTasksEstimated>1</NewTasksEstimated>
      <SplitsInProgressTasks>1</SplitsInProgressTasks>
      <SpreadActualCost>0</SpreadActualCost>
      <SpreadPercentComplete>0</SpreadPercentComplete>
      <TaskUpdatesResource>1</TaskUpdatesResource>
      <FiscalYearStart>0</FiscalYearStart>
      <WeekStartDay>1</WeekStartDay>
      <MoveCompletedEndsBack>0</MoveCompletedEndsBack>
      <MoveRemainingStartsBack>0</MoveRemainingStartsBack>
      <MoveRemainingStartsForward>0</MoveRemainingStartsForward>
      <MoveCompletedEndsForward>0</MoveCompletedEndsForward>
      <BaselineForEarnedValue>0</BaselineForEarnedValue>
      <AutoAddNewResourcesAndTasks>1</AutoAddNewResourcesAndTasks>
      <CurrentDate>2016-02-02T08:00:00</CurrentDate>
      <MicrosoftProjectServerURL>1</MicrosoftProjectServerURL>
      <Autolink>0</Autolink>
      <NewTaskStartDate>0</NewTaskStartDate>
      <NewTasksAreManual>1</NewTasksAreManual>
      <DefaultTaskEVMethod>0</DefaultTaskEVMethod>
      <ProjectExternallyEdited>0</ProjectExternallyEdited>
      <ExtendedCreationDate>1984-01-01T00:00:00</ExtendedCreationDate>
      <ActualsInSync>1</ActualsInSync>
      <RemoveFileProperties>0</RemoveFileProperties>
      <AdminProject>0</AdminProject>
      <UpdateManuallyScheduledTasksWhenEditingLinks>1</UpdateManuallyScheduledTasksWhenEditingLinks>
      <KeepTaskOnNearestWorkingTimeWhenMadeAutoScheduled>0</KeepTaskOnNearestWorkingTimeWhenMadeAutoScheduled>
      <OutlineCodes />
      <WBSMasks />
      <ExtendedAttributes />
      <Calendars>
        <Calendar>
          <UID>1</UID>
          <Name>Standard</Name>
          <IsBaseCalendar>1</IsBaseCalendar>
          <IsBaselineCalendar>0</IsBaselineCalendar>
          <BaseCalendarUID>-1</BaseCalendarUID>
          <WeekDays>
            <WeekDay>
              <DayType>1</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>2</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>3</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>4</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>5</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>6</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
            <WeekDay>
              <DayType>7</DayType>
              <DayWorking>1</DayWorking>
              <WorkingTimes>
                <WorkingTime>
                  <FromTime>08:00:00</FromTime>
                  <ToTime>12:00:00</ToTime>
                </WorkingTime>
                <WorkingTime>
                  <FromTime>13:00:00</FromTime>
                  <ToTime>17:00:00</ToTime>
                </WorkingTime>
              </WorkingTimes>
            </WeekDay>
          </WeekDays>
        </Calendar>
        <Calendar>
          <UID>148840</UID>
          <Name>The</Name>
          <IsBaseCalendar>0</IsBaseCalendar>
          <IsBaselineCalendar>0</IsBaselineCalendar>
          <BaseCalendarUID>1</BaseCalendarUID>
        </Calendar>
      </Calendars>
      <Tasks>
        <Task>
          <UID>0</UID>
          <ID>0</ID>
          <Name>First Project</Name>
          <Active>1</Active>
          <Manual>1</Manual>
          <Type>1</Type>
          <IsNull>0</IsNull>
          <CreateDate>2016-01-12T00:00:00</CreateDate>
          <WBS>0</WBS>
          <OutlineNumber>0</OutlineNumber>
          <OutlineLevel>0</OutlineLevel>
          <Priority>500</Priority>
          <Start>2016-01-12T08:00:00</Start>
          <Finish>2016-02-29T17:00:00</Finish>
        </Task>
        <Task>
          <UID>1</UID>
          <ID>1</ID>
          <Name>Australia</Name>
          <Active>1</Active>
          <Manual>1</Manual>
          <Type>1</Type>
          <IsNull>0</IsNull>
          <CreateDate>2016-01-12T00:00:00</CreateDate>
          <WBS>1</WBS>
          <OutlineNumber>1</OutlineNumber>
          <OutlineLevel>1</OutlineLevel>
          <Priority>500</Priority>
          <StartText />
          <FinishText />
          <DurationText />
          <Start>2016-01-12T08:00:00</Start>
          <Finish>2016-02-29T17:00:00</Finish>
          <ManualStart>2016-01-12T08:00:00</ManualStart>
          <ManualFinish>2016-02-29T17:00:00</ManualFinish>
          <DurationFormat>7</DurationFormat>
          <ResumeValid>0</ResumeValid>
          <EffortDriven>0</EffortDriven>
          <Recurring>0</Recurring>
          <OverAllocated>0</OverAllocated>
          <Estimated>0</Estimated>
          <Milestone>0</Milestone>
          <Summary>0</Summary>
          <DisplayAsSummary>0</DisplayAsSummary>
          <Critical>0</Critical>
          <IsSubproject>0</IsSubproject>
          <IsSubprojectReadOnly>0</IsSubprojectReadOnly>
          <ExternalTask>0</ExternalTask>
          <EarlyStart>2016-02-02T08:00:00</EarlyStart>
          <EarlyFinish>2016-02-02T17:00:00</EarlyFinish>
          <LateStart>2016-02-02T08:00:00</LateStart>
          <LateFinish>2016-02-02T17:00:00</LateFinish>
          <StartVariance>0</StartVariance>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>960000.00</WorkVariance>
          <FreeSlack>0</FreeSlack>
          <TotalSlack>0</TotalSlack>
          <StartSlack>0</StartSlack>
          <FinishSlack>0</FinishSlack>
          <FixedCost>0</FixedCost>
          <FixedCostAccrual>3</FixedCostAccrual>
          <PercentComplete>0</PercentComplete>
          <PercentWorkComplete>0</PercentWorkComplete>
          <Cost>0</Cost>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualDuration>PT0H0M0S</ActualDuration>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualWork>PT0H0M0S</ActualWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <ACWP>0.00</ACWP>
          <CV>0.00</CV>
          <ConstraintType>0</ConstraintType>
          <CalendarUID>-1</CalendarUID>
          <LevelAssignments>1</LevelAssignments>
          <LevelingCanSplit>1</LevelingCanSplit>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>8</LevelingDelayFormat>
          <IgnoreResourceCalendar>0</IgnoreResourceCalendar>
          <HideBar>0</HideBar>
          <Rollup>0</Rollup>
          <BCWS>0.00</BCWS>
          <BCWP>0.00</BCWP>
          <PhysicalPercentComplete>0</PhysicalPercentComplete>
          <EarnedValueMethod>0</EarnedValueMethod>
          <IsPublished>1</IsPublished>
          <CommitmentType>0</CommitmentType>
        </Task>
        <Task>
          <UID>2</UID>
          <ID>2</ID>
          <Name>Kangaroo</Name>
          <Active>1</Active>
          <Manual>1</Manual>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <CreateDate>2016-02-02T08:00:00</CreateDate>
          <WBS>1.1</WBS>
          <OutlineNumber>1.1</OutlineNumber>
          <OutlineLevel>2</OutlineLevel>
          <Priority>500</Priority>
          <ManualStart>2016-01-12T08:00:00</ManualStart>
          <ManualFinish>2016-02-29T17:00:00</ManualFinish>
          <ManualDuration>PT392H0M0S</ManualDuration>
          <Start>2016-01-12T08:00:00</Start>
          <Finish>2016-02-29T17:00:00</Finish>
          <Duration>PT392H0M0S</Duration>
          <ManualDuration>PT392H0M0S</ManualDuration>
          <DurationFormat>7</DurationFormat>
          <Work>PT392H0M0S</Work>
     
          <ConstraintType>4</ConstraintType>
          <CalendarUID>-1</CalendarUID>
          <ConstraintDate>2016-01-12T08:00:00</ConstraintDate>
          <ActualWork>PT117H36M0S</ActualWork>
          <ActualDuration>PT117H36M0S</ActualDuration>
          <RemainingWork>PT274H24M0S</RemainingWork>
          <RemainingDuration>PT274H24M0S</RemainingDuration>
          <ActualStart>2016-01-12T08:00:00</ActualStart>
          <PercentWorkComplete>30</PercentWorkComplete>
          <PercentComplete>30</PercentComplete>
        <ResumeValid>1</ResumeValid>
          </Task>
        <Task>
          <UID>3</UID>
          <ID>3</ID>
          <Name>Platypus</Name>
          <Active>1</Active>
          <Manual>1</Manual>
          <Type>0</Type>
          <IsNull>0</IsNull>
          <CreateDate>2016-02-02T08:00:00</CreateDate>
          <WBS>1.2</WBS>
          <OutlineNumber>1.2</OutlineNumber>
          <OutlineLevel>2</OutlineLevel>
          <Priority>500</Priority>
          <ManualStart>2016-01-13T08:00:00</ManualStart>
          <ManualFinish>2016-02-29T17:00:00</ManualFinish>
          <ManualDuration>PT384H0M0S</ManualDuration>
          <Start>2016-01-13T08:00:00</Start>
          <Finish>2016-02-29T17:00:00</Finish>
          <Duration>PT384H0M0S</Duration>
          <ManualDuration>PT384H0M0S</ManualDuration>
          <DurationFormat>7</DurationFormat>
          <Work>PT384H0M0S</Work>
          <ConstraintType>4</ConstraintType>
          <CalendarUID>-1</CalendarUID>
          <ConstraintDate>2016-01-13T08:00:00</ConstraintDate>
          <ActualWork>PT192H0M0S</ActualWork>
          <ActualDuration>PT192H0M0S</ActualDuration>
          <RemainingWork>PT192H0M0S</RemainingWork>
          <RemainingDuration>PT192H0M0S</RemainingDuration>
          <ActualStart>2016-01-13T08:00:00</ActualStart>
          <PercentWorkComplete>50</PercentWorkComplete>
          <PercentComplete>50</PercentComplete>
          <ResumeValid>1</ResumeValid>
        </Task>
      </Tasks>
      <Resources>
        <Resource>
          <UID>0</UID>
          <ID>0</ID>
          <Type>1</Type>
          <IsNull>0</IsNull>
          <WorkGroup>0</WorkGroup>
          <MaxUnits>1.00</MaxUnits>
          <PeakUnits>0.00</PeakUnits>
          <OverAllocated>0</OverAllocated>
          <CanLevel>1</CanLevel>
          <AccrueAt>3</AccrueAt>
          <Work>PT0H0M0S</Work>
          <RegularWork>PT0H0M0S</RegularWork>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualWork>PT0H0M0S</ActualWork>
          <RemainingWork>PT0H0M0S</RemainingWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <PercentWorkComplete>0</PercentWorkComplete>
          <StandardRate>0</StandardRate>
          <StandardRateFormat>2</StandardRateFormat>
          <Cost>0</Cost>
          <OvertimeRate>0</OvertimeRate>
          <OvertimeRateFormat>2</OvertimeRateFormat>
          <OvertimeCost>0</OvertimeCost>
          <CostPerUse>0</CostPerUse>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <WorkVariance>0.00</WorkVariance>
          <CostVariance>0</CostVariance>
          <SV>0.00</SV>
          <CV>0.00</CV>
          <ACWP>0.00</ACWP>
          <CalendarUID>1</CalendarUID>
          <BCWS>0.00</BCWS>
          <BCWP>0.00</BCWP>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
          <BookingType>0</BookingType>
          <CreationDate>2016-02-02T11:40:00</CreationDate>
          <IsCostResource>0</IsCostResource>
          <IsBudget>0</IsBudget>
        </Resource>
        <Resource>
          <UID>148839</UID>
          <ID>1</ID>
          <Name>The</Name>
          <Type>1</Type>
          <IsNull>0</IsNull>
          <Initials>T</Initials>
          <WorkGroup>0</WorkGroup>
          <MaxUnits>1.00</MaxUnits>
          <PeakUnits>1.00</PeakUnits>
          <OverAllocated>0</OverAllocated>
          <CanLevel>1</CanLevel>
          <AccrueAt>3</AccrueAt>
          <Work>PT16H0M0S</Work>
          <RegularWork>PT16H0M0S</RegularWork>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <ActualWork>PT0H0M0S</ActualWork>
          <RemainingWork>PT16H0M0S</RemainingWork>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <PercentWorkComplete>0</PercentWorkComplete>
          <StandardRate>0</StandardRate>
          <StandardRateFormat>2</StandardRateFormat>
          <Cost>0</Cost>
          <OvertimeRate>0</OvertimeRate>
          <OvertimeRateFormat>2</OvertimeRateFormat>
          <OvertimeCost>0</OvertimeCost>
          <CostPerUse>0</CostPerUse>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <WorkVariance>960000.00</WorkVariance>
          <CostVariance>0</CostVariance>
          <SV>0.00</SV>
          <CV>0.00</CV>
          <ACWP>0.00</ACWP>
          <CalendarUID>148840</CalendarUID>
          <BCWS>0.00</BCWS>
          <BCWP>0.00</BCWP>
          <IsGeneric>0</IsGeneric>
          <IsInactive>0</IsInactive>
          <IsEnterprise>0</IsEnterprise>
          <BookingType>0</BookingType>
          <CreationDate>2016-02-02T11:52:00</CreationDate>
          <IsCostResource>0</IsCostResource>
          <IsBudget>0</IsBudget>
        </Resource>
      </Resources>
      <Assignments>
        <Assignment>
          <UID>1</UID>
          <TaskUID>2</TaskUID>
          <ResourceUID>148839</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualWork>PT0H0M0S</ActualWork>
          <ACWP>0.00</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostRateTable>0</CostRateTable>
          <RateScale>0</RateScale>
          <CostVariance>0</CostVariance>
          <CV>0.00</CV>
          <Delay>0</Delay>
          <Finish>2016-02-29T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>480000.00</WorkVariance>
          <HasFixedRateUnits>1</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>7</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT384H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT384H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2016-01-12T08:00:00</Start>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0.00</VAC>
          <Work>PT384H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0.00</BCWS>
          <BCWP>0.00</BCWP>
          <BookingType>0</BookingType>
          <BudgetCost>0</BudgetCost>
          <BudgetWork>PT0H0M0S</BudgetWork>
        </Assignment>
        <Assignment>
          <UID>2</UID>
          <TaskUID>3</TaskUID>
          <ResourceUID>148839</ResourceUID>
          <PercentWorkComplete>0</PercentWorkComplete>
          <ActualCost>0</ActualCost>
          <ActualOvertimeCost>0</ActualOvertimeCost>
          <ActualOvertimeWork>PT0H0M0S</ActualOvertimeWork>
          <ActualWork>PT0H0M0S</ActualWork>
          <ACWP>0.00</ACWP>
          <Confirmed>0</Confirmed>
          <Cost>0</Cost>
          <CostRateTable>0</CostRateTable>
          <RateScale>0</RateScale>
          <CostVariance>0</CostVariance>
          <CV>0.00</CV>
          <Delay>0</Delay>
          <Finish>2016-02-29T17:00:00</Finish>
          <FinishVariance>0</FinishVariance>
          <WorkVariance>480000.00</WorkVariance>
          <HasFixedRateUnits>1</HasFixedRateUnits>
          <FixedMaterial>0</FixedMaterial>
          <LevelingDelay>0</LevelingDelay>
          <LevelingDelayFormat>7</LevelingDelayFormat>
          <LinkedFields>0</LinkedFields>
          <Milestone>0</Milestone>
          <Overallocated>0</Overallocated>
          <OvertimeCost>0</OvertimeCost>
          <OvertimeWork>PT0H0M0S</OvertimeWork>
          <RegularWork>PT376H0M0S</RegularWork>
          <RemainingCost>0</RemainingCost>
          <RemainingOvertimeCost>0</RemainingOvertimeCost>
          <RemainingOvertimeWork>PT0H0M0S</RemainingOvertimeWork>
          <RemainingWork>PT376H0M0S</RemainingWork>
          <ResponsePending>0</ResponsePending>
          <Start>2016-01-13T08:00:00</Start>
          <StartVariance>0</StartVariance>
          <Units>1</Units>
          <UpdateNeeded>0</UpdateNeeded>
          <VAC>0.00</VAC>
          <Work>PT376H0M0S</Work>
          <WorkContour>0</WorkContour>
          <BCWS>0.00</BCWS>
          <BCWP>0.00</BCWP>
          <BookingType>0</BookingType>
          <BudgetCost>0</BudgetCost>
          <BudgetWork>PT0H0M0S</BudgetWork>
        </Assignment>
      </Assignments>
    </Project>

    After open it in Project, I see that % is differ slightly, not 30 and 50, but 31 and 51. I guess it because calendar settings - when I reexport to xml, there is not woking weekends and durations changed, from PT384H0M0S to PT376H0M0S for example.

    Also Project hangs when I click "Change working time".

    What's wrong with that xml?

    Tuesday, February 2, 2016 3:48 PM

Answers

  • I figured out that without first Resource (uid 0) in xml "Change working time" opens in my Project.
    • Marked as answer by sm g Wednesday, February 3, 2016 3:34 AM
    Wednesday, February 3, 2016 2:43 AM

All replies

  • sm g,

    There have been some issues with XML. First, make sure you have the latest update applied, for Project 2013 that is the January 2016 update (see: https://blogs.technet.microsoft.com/projectsupport/p/msp13/). The easiest way to update is to run a Windows update.

    John

    Tuesday, February 2, 2016 5:48 PM
  • John,

    I installed that update and nothing changed. Same problem with that xml occurs in Project 2010 and 2007.

    Wednesday, February 3, 2016 1:24 AM
  • sm g,

    Not sure what to tell you. I copied your XML file verbatim to Notpad and then used Save As with UTF-8 encoding to my documents folder. I then opened with Project 2010 Pro. The file opened in Project without problems and I was able to change the working time with no hang up. So what exactly is the problem?

    John

    Wednesday, February 3, 2016 2:21 AM
  • I figured out that without first Resource (uid 0) in xml "Change working time" opens in my Project.
    • Marked as answer by sm g Wednesday, February 3, 2016 3:34 AM
    Wednesday, February 3, 2016 2:43 AM
  • sm g,

    Interesting, because it worked fine for me with resource uid 0 included, just as you show in your original post.

    But, glad you got it working.

    John

    Wednesday, February 3, 2016 3:36 PM