  • Hi All,

             I posted a query a couple of months ago relating to the location of the project time phased data (BCWS, BCWP and ACWP). I got a reponse (from Diego Campos Pereira) suggesting I check the task or assignment time phased data sets. I did this and explored other data tables as candidate to located time phased performance data.

    At the moment I believe 

    • TaskBaselineTimephasedDataSet.TaskBaselineCost = BCWS
    • TaskTimephasedDataSet.TaskActualCost = ACWP

    I was hoping

    1. Someone could confirm this the two bullets above?
    2. Someone could suggest where I would locate BCWP

    For something as fundamental as Earned Value I would have expected locating this data to be much much easier.
    Thanks

    Tony