Automatic Resource % Allocation of Parallel/Simultaneous Tasks RRS feed

  • Question

  • Hi All,

    I am trying to figure out how to get Project to the following:

    I have 4 machine resources that need to accomplish 5 fixed work tasks. Each task starts one week after the previous one. In the first week I will have only one task which will take up 100% of the resources; in the second week two tasks will be running therefore 50% will be given to each task; 3rd will be 33.33% per task and so on. Given that these are fixed work tasks I want project to automatically distribute percentages of the machines resource to the tasks and then compute the end date.

    Please let me know if anyone knows how to do this.

    Thanks,

     

    Monday, October 10, 2011 7:17 PM