none
After Migration PS2003 to PS2010 SP1 We are Losing Baselines After Publish RRS feed

  • Question

  • We just Migrated from PS2003 to PS2010 SP1 through PS2007.  We have update quite a few Tasks on current work in process projects and Now have discovered this same issue with missing Baseline 0 data.  It only appears on projects that are being Published after the migration.

    I see this was a problem back in YR2010.  I posted a query on that older answer as well. Has this ever been corrected or is there any way to avoid this problem?

    Forrest

    Tuesday, March 6, 2012 10:33 PM

Answers

  • This helps TREMENDOUSLY!

    I'm trying to recover some of my Baseline by Copy & Pasting from PS2003 to PS2010 projects where we lost this data and then republishing do you see any problem with this?

    Thanks so much for the response.

    Forrest

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Thursday, March 8, 2012 4:15 PM
  • Hi Forrest,

    maybe you can create a macro in order to do this work automatically. 

    There can be the steps:

    • Connect on PS2010
    • Read Project
    • Read BaselineTimephased by OleDB from a 2007 Reporting dabatase
    • Write BaselineTimphased on 2010
    • Save and Publish

    I hope this can helps you,

    Best Regards

    Paolo O.

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Sunday, March 11, 2012 5:06 PM
  • Hi Paolo

    This is a good suggestion.

    Thank you

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Monday, March 12, 2012 2:10 PM

All replies

  • I believe the issue still exists as far as I'm aware. This is caused only where a set of users publishing the schedule for the first time do not hae permission to save the protected baseline. So the work around would be to either open and publish all projects once under an administrator account. From that point on things will be fine. Alternative is to allow groups to save protected baseline until you can confirm all projects have been published at least once. You can add the 'Last Published' column in the project centre to govern this. Quite a nasty litte bug this one. Hope this helps.

    Regards,

    Piet Remen
    http://pietremen.blogspot.com.au

    Thursday, March 8, 2012 3:59 PM
  • This helps TREMENDOUSLY!

    I'm trying to recover some of my Baseline by Copy & Pasting from PS2003 to PS2010 projects where we lost this data and then republishing do you see any problem with this?

    Thanks so much for the response.

    Forrest

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Thursday, March 8, 2012 4:15 PM
  • Hi Forrest,

    maybe you can create a macro in order to do this work automatically. 

    There can be the steps:

    • Connect on PS2010
    • Read Project
    • Read BaselineTimephased by OleDB from a 2007 Reporting dabatase
    • Write BaselineTimphased on 2010
    • Save and Publish

    I hope this can helps you,

    Best Regards

    Paolo O.

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Sunday, March 11, 2012 5:06 PM
  • Hi Paolo

    This is a good suggestion.

    Thank you

    • Marked as answer by Forrest Monday, March 12, 2012 2:10 PM
    Monday, March 12, 2012 2:10 PM