cannot add w new filter view to master project (in the "project center" view) RRS feed

  • Question

  • Hi,

    working with PWA 2010.

    I prepared a new filter on the PWA which filtered the tasks by a word in the "task name".

    in all the project files it works.

    in the master project it doesnt filter and I receive a blank view.

     

    is it possible to filter a master project?

     

    Thanks,

    Hanni

     

    P.S can I filter in the PWA in a way that the summary task for the filtered tasks will appear?



    Hanni, PMO
    Monday, May 30, 2011 6:35 AM

All replies

  • Hello Hanni,

    Did you try to see this in Task Summary view? Please make sure to have Outline as "All Outline levels" once you are in Project views in PWA.

    I have verified that by clicking the Subproject check box on the ribbon of Project center

    Does that help?


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82