  • We're planning to move our SCCM 2012 SP1 installation to a new VM running Server 2012 R2. We're planning on keeping the same server name so the Site Backup and then restore looks like it will work for us. We'd also like to move the DB to a new, remote, SQL 2012 box. Does the DB need to be restored to a SQL box with the same name as well?


    Orange County District Attorney

    Thursday, January 2, 2014 11:46 PM

Answers

  • No sql does not need to be reinstalled on the same server but you might want to do it as a two step process. Move SQL then move the CM server.

    http://www.enhansoft.com/

    Friday, January 3, 2014 2:35 AM

All replies

  • No sql does not need to be reinstalled on the same server but you might want to do it as a two step process. Move SQL then move the CM server.

    http://www.enhansoft.com/

    Friday, January 3, 2014 2:35 AM
  • Thanks Garth. That sounds good. I'm leaning toward moving the DB first and then just restoring the site only.

    Orange County District Attorney