    im new to project and getting along fine for the time being, but im trying to do a report on one of my projects and it keeps showing me all the resources and there total time used , i just want to see which resources were used and for how long on this indivual  job

    thanks very much

    Thursday, February 20, 2014 4:01 PM

Answers

  • Todski,

    Are you working with a resource pool and sharer files?  If so, open the sharer file and when the dialog pops up asking whether you want to open the resource pool, choose "Do not open other files."

    That should show you only resources assigned to tasks in the current file.