  • Hello Dears,

    I have an action workflow on MIM portal that sends an email notification when a new user created.

    a have defined a "transition in" MPR, so the workflow sends the email at 1:00 AM.

    is there any way to change this action time to be for example  at 11:00 AM ??

    Many thanks in advance :)


    • Edited by randa sa Sunday, February 4, 2018 11:03 AM
    Sunday, February 4, 2018 11:02 AM

Answers

  • You're probably running into the schedule that the SQL Agent job for set maintenance runs on. You can change that schedule. You could also edit the xpath filter for the set where I believe you can edit the timestamp.

    Thanks,
    Brian