Assignment custom field (Project Server 2013) RRS feed

  • Question

  • Hi,

    I created an ECF entity Task, with a drop down list.

    I selected values for each assignment in the Task view.

    In Project Pro, when I look at the field in the Task Usage, it is empty.

    What am I missing?

    Thanks

    Friday, May 27, 2016 5:27 PM

Answers

  • Hi,

    You have to specify in the custom field settings the behavior for the assignment. By default, the value will not roll down to assignment level, you have a specifically configure it. See below the option to set (it is in french but I remember you are french speaking). Once done, the value will appear on assignment rows in the task usage.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, MCC |

    • Marked as answer by WLID1966 Monday, May 30, 2016 7:42 AM
    Monday, May 30, 2016 7:35 AM