Resource capacity calculating incorrectly RRS feed

  • Question

  • I have a Project Server 2013 Development Environment that should replicate my production environment.  In both environments, Resource Capacity is set to calculate based on the Resource Base Calendar.  In the production environment, the resource capacity is showing as 8 hours per day on Workdays (Monday - Friday that are not holidays).

    In the Development Environment, capacity is showing as 23.983 hours per day everyday of the week except when a holiday occurs.  When a holiday occurs, the capacity is shown as 0 hours on the holiday and the prior "Workday" the hours is shown as 7 hours, ie. for Memorial Day I see 0 hours, on Sat and Sun prior I see 23.983 hours and on Friday prior I see 7 hours.

    Any idea on why this is happening?

    Friday, April 22, 2016 1:09 PM