  • Question

  • I currently have a Project set up that includes multiple sub-projects. I want to use one resource pool for all the sub-projects but I am having trouble getting this to work. how can this be achieved?
    Monday, February 16, 2015 12:32 AM

All replies

  • N.Isaac,

    can you be a little more specicifc as to what is the method you are employing and the trouble you are experiencing?

    In order to use one resource pool, you need to set up a Shared Resource Pool, and use the same pool across all sub-projects.

    here is some guidance on how to do it: https://support.office.microsoft.com/en-us/article/Create-and-share-a-resource-pool-64a2416e-b811-4ddf-b039-e0347e233581?CorrelationId=552b031b-6431-4a81-9d7c-c38b3735fae1&ui=en-US&rs=en-US&ad=US


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Monday, February 16, 2015 6:31 AM
    Moderator
  • Linked Master file and linked resource pool = high risk of file corruption.

    Make sure you never:

    • Rename
    • Move
    • Over-write

    any linked file and store the files ONLY on a disk drive that's in the same physical building as yours and not on any disk on the WAN.

    Otherwise its not if but when one or more files will corrupt.


    Rod Gill
    Author of the one and only Project VBA Book
    www.project-systems.co.nz

    Tuesday, February 17, 2015 8:17 PM