Add % allocated to bars in Team Planner - MSP 2010 RRS feed

  • Question

  • I want to be able to view the Resource's % Allocated IN the bar along with the task name - is that possible?

    RM Kunhardt

    Thursday, February 22, 2018 5:50 PM

All replies

  • Bob,

    Unfortunately, no. In Project 2010 the team planner view has a fixed bar style with no means (that I know of) to custom format the bars. Whether expanded formatting for Team Planner bars is available in later versions of Project, I do not know.

    John

    Thursday, February 22, 2018 6:54 PM
  • Thanks for your reply John,

    I suppose I should have framed my question as "Can anyone program MSP to do this".  I have seen some independents such as OnePager get in the back door and do some pretty incredible things.  I'm looking for that person.


    RM Kunhardt

    Friday, February 23, 2018 12:49 PM
  • Bob,

    You're welcome and thanks for the feedback.

    Again, I don't know if later version of Project have expanded Team Planner formatting capability, perhaps someone else will jump in and address that.

    Perhaps you should contact OnePager and open a dialogue with them but this isn't the forum for doing that.

    John

    Friday, February 23, 2018 3:14 PM