Resource Manager Timesheet Approval gets mysterious Confirmation box with routing to next approver (PS 2010) RRS feed

  • Question

  • Hi

    We are on our second round of buildout /configuration of Project Server 2010 in the DEV environment. We have configured single entry mode; Task Status Manager Approval is enabled, with "Require line approval before timesheet approval" also turned on.

    It all appears to be working as before, except that when the resource manager approves a timesheet, on approval he gets a "confirmation" dialogue box prompting for the name of a user to: "Send timesheet to:" as well as soliticing comments. In our previous sandbox configuration, when the timesheet was approved, there was no further steps, no "Send timesheet to:".  How do we turn this off???

    Carl


    Thursday, May 17, 2012 9:13 PM

Answers

All replies