Resources changing planned work RRS feed

  • Question

  • Hello,

    Is there any way that a resource can alter the scheduled/planned work for a task, maybe through Timesheeting or the "Tasks" page.

    It would be useful for resources to be able to do this.

    Thnx

    Jeff

    Monday, November 28, 2016 3:35 AM

All replies

  • Hello,

    Resources cant change planned work, however they can request a change to planned work while reporting input using actuals and remaining work field, either through timesheet or my tasks page.

    whats a reason to such an expectation? 

    cheers.