location of 'Successor' and 'Predecessor' of tasks in project server 2010 RRS feed

  • Question

  • Where the 'Successor' and 'Predecessor' of tasks are saved in the project server 2010 database and in which table ?

    Monday, February 18, 2013 12:32 PM

All replies

  • You can find this information in Draft/Published database in MSP_links table. However Microsoft do not recommend querying information directly from Draft and Published database. 

    Thanks,

    Kiran K.