Timesheet for those without resources RRS feed

  • Question

  • Hello,

    I have a scenario here and would like to help one of you to help me look and see if its implementation is feasible.

    There is a customer of the company where I work that needs to control the availability of resources, only those resources are not allocated to projects but serve on demanda.É can create a timesheet for those without resources they are allocated to projects to control their availability, hours of work days and overtime.

    If there are other suggestions I am grateful to know.

    Thanks.


    Hezequias Vasconcelos

    Thursday, April 26, 2012 7:59 PM

All replies

  • Hi Hezequias--

    As I understand that you want to assign a resource on a project on demand basis but what do you mean by "É can create a timesheet for those without resources they are allocated to projects to control their availability, hours of work days and overtime." could you please explain in some more details?


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    Friday, April 27, 2012 6:05 AM
  • Hi Amit Khare,

    In fact the demand is not part of the project, but I need to control the resource availability in EPM 2010. You can do this?
    Another point is how many hours they need to control the resource as holidays, working hours and overtime I thought I would maybe use a timesheet to
    fulfill this task. Do not know if it's possible and the opnion of you would like to see how to use the EPM 2010 in this scenario.

    Thanks for the help.


    Hezequias Vasconcelos

    Friday, April 27, 2012 10:58 AM