Pulling a Report by Stage RRS feed

  • Question

  • In the Stage Gate process we need to pull all of our reports by Stage in the process not by any certain dates. I have found areas where I can get total hours per resource by month or summary task however it is not exactly what I need.

    I am looking to see each resource and how many hours are required of them by each stage (preferably a total line). 

    Any Ideas?

    Any other reports that people use for Stage Gate would be helpful knowledge as well.  Thank you!

    Friday, April 15, 2016 6:01 PM

All replies

  • MayMegan3536,

    Have you tried using Project's grouping functionality? You should be able to group by stage in either the Task Usage or Resource Usage view and get the totals per stage that you want on the group summary lines. And if you need it further broken down by stage by resource, then use two levels of grouping.

    Hope this helps.

    John