duration on MSP 2007 RRS feed

  • Question

  • Hi all,

    I started a task on march one. duration is 2 days. So as per my knowledge, task end date must be march 2 (march 1 and 2 -two days we worked). But if i give duration 2 days, end date automatically coming as March 3.

    Please help.

    ananth 

    Thursday, March 1, 2012 10:12 AM

Answers

  • Hi,

    two possible reasons come to my mind:

    1. Start time is not 8am, which will cause the system to use some hours on 3rd of March. Check in Tools - Options - View and change Date format to display hours.

    2. A resource is assigned with no capacity on March 2nd. Could this be the case?

    Regards
    Barbara

    Thursday, March 1, 2012 10:38 AM