    I was wondering how PS 2013 would behave if we delete a project schedule that had actual hours reported against it. I am reading a Custom report from timesheet table for actuals and overtime and since the project was removed I dont get total no. of hours same as before. Any tip how can I bring it back or how can that be treated to fill the gap of no. of hours....


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, June 11, 2015 11:59 AM

Answers

  • Hi Syed,

    I'm not a developer so maybe my reply is not relevant, but I can see that you are querying the MSP_EpmProject_UserView. Since you delete the project, it will not be anymore in this table thus it seems normal that the query cannot return the actuals still in the timesheet.

    Why not retrieving all data only from the timesheet views/tables. For example the dbo.MSP_TimesheetLine_UserView will contain by period the actual/overtime/billable/non billable, the planned work, the project name, the resource name, task name, class type, status...


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Thursday, June 11, 2015 12:25 PM
    Moderator

All replies

  • My Query is 


    SELECT 
     distinct(TLUV.[ResourceName])
      ,TLUV.[ProjectName]
    ,[WorkOrderNo.] as EmployeeNo
      ,[Resource Departments]
       

     ,Sum([ActualWorkBillable]) as ActualBillable

          ,Sum([ActualOvertimeWorkBillable]) as OverTimesBillable
    ,[WBS No.]
    ,[Fund Category]

      FROM [PWA_ITProjects].[dbo].[MSP_TimesheetLine_UserView] as TLUV
    , MSP_EpmProject_UserView as PUV
    , MSP_EPMResource_UserView as RUV
      where 

      [Resource Departments] in (@ResourceDepartment)
      and PeriodName in (@TSMonth)
    and [Employee Type]='Contractor'
    AND tluv.rESOURCEnAME IN (@ResourceName)
     and TLUV.ProjectUID=PUV.ProjectUID
     and TLUV.ResourceUID=RUV.ResourceUID
     
      group by 

     TLUV.Projectname, TLUV.Resourcename, PeriodName
    ,[WorkOrderNo.]
     ,[WBS No.]
     ,[Fund Category]
     , [Resource Departments]
     order by TLUV.ProjectName


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS

    Thursday, June 11, 2015 12:00 PM
  • Hi Syed,

    I'm not a developer so maybe my reply is not relevant, but I can see that you are querying the MSP_EpmProject_UserView. Since you delete the project, it will not be anymore in this table thus it seems normal that the query cannot return the actuals still in the timesheet.

    Why not retrieving all data only from the timesheet views/tables. For example the dbo.MSP_TimesheetLine_UserView will contain by period the actual/overtime/billable/non billable, the planned work, the project name, the resource name, task name, class type, status...


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Thursday, June 11, 2015 12:25 PM
    Moderator
  • Hi Guillaume,

    Thanks for the tip, it did help me out in resolving the observation. 


    Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS