How do I change Resource Cost Center only and retain historical cost center data? RRS feed

  • Question

  • How would a Project Server Admin accommodate changes in the resource's cost center itself?

    For example, Ken (timesheet submitter) records Feb time in cost center C1, but then transfers to a new team, which is in cost center C2 on Mar 1st.

    When I change his cost center at the resource level, reporting indicates all of his previous C1 time as a resource under the C2 cost center, and all of his C1 time looks like it's incorrectly in C2.

    I am thinking about adding custom resource fields to track these changes, but it seems like a lot of extra work, if something already exists that I can use.

    Thanks,

    Marty


    Thursday, March 26, 2015 6:13 PM

All replies

  • Marty,

    AFAIK, there is no way to do this OOB as Resource Fields are not 'time-phased'.

    A 'possible' alternative, like you mentioned, could be be to use custom fields to track, the change (like Effective Date, Old Cost Center), and then somehow write a query to consider the old cost center between the dates. I have not tried this personally, just a thought.


    Cheers,

    Prasanna Adavi, Project MVP