none
Hours showing up in TimeSheet for every day instead of a week RRS feed

  • Question

  • I am in Ms Project 2007.  I have assigned 10 hours for a task from 2/3 to 2/7.  In time sheet it shows as 2.5 hours per day.  This forces me to enter 2.5 hours per day. Instead, i do not want PWA to show for every day.  It should show a bulk of 10 hours and i should be able to put the hours as i want.

    How to do this.  Any help would be appreaciated.

    Thanks,

    NSG.


    NSG12

    Tuesday, February 4, 2014 6:03 PM

All replies

  • Hi NSG12,

    You can configure this option in the timesheet settings from the server settings page. Please refer to this post: http://technet.microsoft.com/en-us/library/cc197630(v=office.12).aspx

    that explains this option: 

    • Timesheet Grid Column Units. Option that controls whether cells in the grid represent one day or one week.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Saturday, February 8, 2014 4:24 PM
    Moderator