Timesheet manager changed after timesheet is submitted RRS feed

  • Question

  • Hi,

     Timesheet manager changed after timesheet is submitted but pending for approval ,Is there a way without resubmitting timesheet, To get approval from new manager in pwa 2010?

    Thursday, March 27, 2014 2:10 PM

All replies

  • Hi Project Help,

    In case you changed the timesheet manager after submission evenif it hasn't been approved, I'm afraid that you'll have to recall the timesheet and submit it again in order for the timesheet to be redirected correctly to the new timesheet manager.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Thursday, March 27, 2014 2:17 PM
    Moderator
  • I completely agree with Guillaume , recalling and resubmitting the timesheet would be easiest fix for this scenario


    Hrishi Deshpande Senior Consultant

    Sunday, March 30, 2014 12:09 AM
    Moderator