    I am looking at the reporting process of DPM, is there a way I can go back a year and run a report for a month out of the year for disk backups?

    I cannot seem to find this option unless its under the Schedule option. But when i try that it says you cannot go back 328 days.

    Thursday, February 7, 2013 6:34 PM

Answers

  • Hi,

    DPM only maintain job history for 30 days, so you would need to run reports on a monthly or less schedule and then look at past reports.


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. Regards, Mike J. [MSFT] This posting is provided "AS IS" with no warranties, and confers no rights.