How can I add additional time to a Task for everyone under that task easily RRS feed

  • Question

  • We are running MS Project server 07.  We are having an issue or lack of knowledge.  We have several tasks in our schedules that need to have additional time added to them.  But if we just increase the duration or the finish date of the task it will add additional time to the 1st resource of the task but it will not spread the additional time to all the resources.  We could go through each of them and manually add additional hrs to their remaining work, but there has to be another method.

     

    Thanks in advance.

    Robert

    • Moved by Ben Howard [MVP]MVP, Moderator Thursday, May 5, 2011 9:23 PM This is more likely a project scheduling issue rather than project server, so moving to the correct forum. (From:Project Server - Setup, Upgrade, Administration and Operation)
    Thursday, May 5, 2011 6:20 PM

Answers

  • Hi Robert,
    Welcome to this Microsoft Project forum:)
    Try splitting the screen and changing the duration there - you can see the result of changing various parameters in the bottom screen. You might like to have a look at my free series for beginners on Microsoft Project in the TechTrax ezine, particularly #5 & 10 on resource assignments, at this site: http://tinyurl.com/2xbhc  or this: http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23 
    (Perhaps you'd care to rate the article before leaving the site, :)  Thanks.)
    FAQs, companion products and other useful Project information can be seen at this web address: <http://www.mvps.org/project/>
    Hope this helps - please let us know how you get on :)
    Mike Glen
    MS Project MVP
     
    Friday, May 6, 2011 3:14 PM