  • For the longest time, I had to run backups manually because they would not start as scheduled (Mondays at 9:00 PM).  I then defined a task to display a message and scheduled it to run 5 minutes before the start of the backups (Mondays 8:55 PM).  This too would not start.  Through pure coincidence, I happened to be logged-on today Monday at 10:30 PM and both the test message and the backups started approximately 90 minutes after their scheduled time and 5 minutes apart.  The Scheduler's "clock" seems to be off, how do I fix ?   Running Vista SP2, maintenance is current.  The computer clock is set correctly and with the correct time zone

    Thanks,
    Zach


    • Edited by zxk1 Tuesday, September 6, 2011 3:11 AM
    Tuesday, September 6, 2011 3:09 AM

Answers

  • Hi,

    Please refer to "Scheduled tasks are delayed in Windows Server 2008 or in Windows Vista" and apply the hotfix:

    http://support.microsoft.com/kb/982341

    Regards,


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. ”
    • Proposed as answer by pkn2011 Thursday, September 15, 2011 8:28 AM
    • Marked as answer by zxk1 Tuesday, September 20, 2011 1:39 AM
    • Unmarked as answer by zxk1 Tuesday, September 20, 2011 1:39 AM
    • Marked as answer by zxk1 Tuesday, September 20, 2011 1:40 AM
    Wednesday, September 14, 2011 9:29 AM
    Moderator

All replies

  • Hi,

    Please refer to "Scheduled tasks are delayed in Windows Server 2008 or in Windows Vista" and apply the hotfix:

    http://support.microsoft.com/kb/982341

    Regards,


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. ”
    • Proposed as answer by pkn2011 Thursday, September 15, 2011 8:28 AM
    • Marked as answer by zxk1 Tuesday, September 20, 2011 1:39 AM
    • Unmarked as answer by zxk1 Tuesday, September 20, 2011 1:39 AM
    • Marked as answer by zxk1 Tuesday, September 20, 2011 1:40 AM
    Wednesday, September 14, 2011 9:29 AM
    Moderator
  • Hi,

    Please refer to "Scheduled tasks are delayed in Windows Server 2008 or in Windows Vista" and apply the hotfix:

    http://support.microsoft.com/kb/982341

    Regards,


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. ”


    Will apply the hotfix and let you know the results....this will take about 1 week.

    zach

    Friday, September 16, 2011 2:38 AM
  • Mago,

    Thanks, the hotfix corrected the problem.

    zxk1