Automatically adjust the start and finish dates for new projects - MS Project 2016? RRS feed

Answers

  • CanucKoz,

    For Project 2016 go to Project > Schedule group > Move Project icon.

    Or, if it's a template and all tasks are linked in a logical sequence without constraints and no actuals are entered, simply reset the Project Start Date under Project > Properties group > Project Information > Start Date.

    Hope this helps.

    John


    • Edited by John - Project Monday, October 9, 2017 1:47 AM more
    • Marked as answer by CanucKoz Monday, October 9, 2017 2:43 AM
    Monday, October 9, 2017 1:41 AM

All replies

  • CanucKoz,

    For Project 2016 go to Project > Schedule group > Move Project icon.

    Or, if it's a template and all tasks are linked in a logical sequence without constraints and no actuals are entered, simply reset the Project Start Date under Project > Properties group > Project Information > Start Date.

    Hope this helps.

    John


    • Edited by John - Project Monday, October 9, 2017 1:47 AM more
    • Marked as answer by CanucKoz Monday, October 9, 2017 2:43 AM
    Monday, October 9, 2017 1:41 AM
  • Exactly what I'm looking for.

    Thanks John!

    Monday, October 9, 2017 2:44 AM
  • CanucKoz,

    You're welcome and thanks for the feedback.

    John

    Monday, October 9, 2017 3:59 AM