How Do I calculate days behind or Ahead at the Summary Level RRS feed

  • Question

  • I know how to do it at the task level using this formula that I got from the internet and it work great the the task level but not at the summary level. 

    int((ProjDateDiff([Start],[Finish])/480)*([% Complete])/100)-int(projdatediff([Start],now())/480)

    Tuesday, October 9, 2012 3:53 PM

Answers

All replies