Can Project Server auto-level RRS feed

  • Question

  • Can I configure PS2010 to not allow a resource to be assigned to a project task if that resource is already assigned elsewhere infor another project  that same period of time? This is to answer repeated questions I get from potential clients in relation to the solution performing the role of "resource manager" instead of a human in smaller organisations.

    thanks in advance.

    Wednesday, May 2, 2012 3:08 PM

Answers

All replies

  • Stev Scott42 --
     
    The answer to your question is no; you cannot prevent PMs from assigning resources to tasks if the resource is already assigned to tasks during the same time period in other projects.  Hope this helps.
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by Stev Scott42 Wednesday, May 2, 2012 7:31 PM
    Wednesday, May 2, 2012 5:36 PM
    Moderator
  • thanks Dale, I thought so but just wanted to be sure.   I will therefore continue to bang the "you need a process" drum rather than expect a solution that makes decisions automatically.

    cheers

    Steve

    Wednesday, May 2, 2012 7:31 PM
  • Steve --
     
    Yup, bang that drum, my friend!  This is one of many issues with Project Server 2010 that are best addressed with a standardized methodology or process.  And you are more than welcome for the help, my friend!  :)
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, May 2, 2012 8:57 PM