Time Line in Project Centre does not appear to syncronize with the Projects Data Filter or View currently selected RRS feed

  • Question

  • Whilst the Timeline in Project Centre is a nice feature,  it does not appear to be related to the project data filter set or the selected Project View - Thus switching one view to another does not change the timeline view - Is this correct?

    If it is, I cannot see much benefit in the timeline view in Project centre, as its not going to be helpful if you have a large set of projects -can you confirm this ( MS Project allows muliti limeline views to be set up for a specific prooject which is basically what Im trying to do in Project Centre)

    Tuesday, April 15, 2014 5:28 AM

All replies

  • Hi Brendan,

    Indeed the timeline feature in the Project Center doesn't work with views and/or filters. This objective is that the user can display in the timeline any of projects he has visibility on regardless of the view (he might not have any control on the view settings), depending on his interest.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    Tuesday, April 15, 2014 11:39 AM
    Moderator
  • In addition, on those projects' tasks appear in the timeline for which you have the open project permission. This may allow you some control&"filtering". It is intended for a quick top-level portfolio overview.

    If you have no use at all for it, you may edit the page and minimize the web part.

    Kind regards,
    Adrian

    Friday, April 18, 2014 9:44 PM