difference between fixed units and fixed work RRS feed

  • Question

  • when I add a new task as a fixed unit with effort driven the ms project deal with it as fixed work why???????


    • Edited by Abd.Alhamad Monday, August 29, 2016 10:02 AM
    Monday, August 29, 2016 9:42 AM

Answers

  • Can you please give us your case so we can reproduce it? 

    Basically if you create the 2 same tasks in a blank project, 1 fixed unit, 1 fixed work:

    If you increase the work from 5 to 6 days both tasks, the fixed units task will have the duration changed to 6 days, and the fixed work task will keep 5d for the work but the unit will decrease.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, August 29, 2016 10:13 AM
    Moderator

All replies

  • Can you please give us your case so we can reproduce it? 

    Basically if you create the 2 same tasks in a blank project, 1 fixed unit, 1 fixed work:

    If you increase the work from 5 to 6 days both tasks, the fixed units task will have the duration changed to 6 days, and the fixed work task will keep 5d for the work but the unit will decrease.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Monday, August 29, 2016 10:13 AM
    Moderator
  • thank u 

    it was really helpful

    Tuesday, August 30, 2016 9:09 AM