complex resource allocation in MSP 2013 RRS feed

  • Question

  • Hi all

    I have used MSP before but not for years.  I have some long term tasks and i would like to allocate varying quantities of resource requirement each month on thse tasks - can i do this in MS Project 2013 or any tips would be greatly appreciated.

    I have had a good look online and so far found nothing.

    Thanks to all - Tom 


    Friday, November 18, 2016 2:19 PM

All replies

  • Hi Tom,

    I'd suggest to use the task usage or resource usage view. It allows you having an excel-like timephased grid (you can set the timescale -day, week, month, quarter, year- from the view tab) where you can manually enter the workload per time period and per assignments.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    • Proposed as answer by Erik van Hurck Wednesday, November 23, 2016 8:51 AM
    Friday, November 18, 2016 2:28 PM