Close Task to Update (2013) RRS feed

Answers

  • Hi Robert,

    In Project 2013, the "close task to update" has been changed!

    It is now the "locked" capability that behaves the same manner. Basically you choose to lock a task in a PWA project view. Consequently you have to previously add the field "lock" to a view. By default the "lock" field will be set to "no". You just have to edit the field and change the value to "yes" for the tasks you want to lock.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS


    Thursday, October 31, 2013 12:25 PM
    Moderator

All replies

  • Hi Robert,

    In Project 2013, the "close task to update" has been changed!

    It is now the "locked" capability that behaves the same manner. Basically you choose to lock a task in a PWA project view. Consequently you have to previously add the field "lock" to a view. By default the "lock" field will be set to "no". You just have to edit the field and change the value to "yes" for the tasks you want to lock.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS


    Thursday, October 31, 2013 12:25 PM
    Moderator
  • Guillaume, hello!

    How can I lock tasks in Project Pro 2013/2016?

    Thanks in advance.


    Tuesday, November 15, 2016 3:28 PM
  • No it is only possible in PWA (web access). In MS Project Pro, you can only unpublish the tasks.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Tuesday, November 15, 2016 3:47 PM