Hi Robert,
In Project 2013, the "close task to update" has been changed!
It is now the "locked" capability that behaves the same manner. Basically you choose to lock a task in a PWA project view. Consequently you have to previously add the field "lock" to a view. By default the "lock" field will be set to "no". You just have to edit the field and change the value to "yes" for the tasks you want to lock.
Hope this helps.
Guillaume Rouyre - MBA, MCP, MCTS
- Edited by Guillaume Rouyre [MBA, MVP, MCC]MVP Thursday, October 31, 2013 12:26 PM
- Marked as answer by Robert6156 Thursday, October 31, 2013 9:16 PM
Thursday, October 31, 2013 12:25 PM
All replies
-
Hi Robert,
In Project 2013, the "close task to update" has been changed!
It is now the "locked" capability that behaves the same manner. Basically you choose to lock a task in a PWA project view. Consequently you have to previously add the field "lock" to a view. By default the "lock" field will be set to "no". You just have to edit the field and change the value to "yes" for the tasks you want to lock.
Hope this helps.
Guillaume Rouyre - MBA, MCP, MCTS
- Edited by Guillaume Rouyre [MBA, MVP, MCC]MVP Thursday, October 31, 2013 12:26 PM
- Marked as answer by Robert6156 Thursday, October 31, 2013 9:16 PM