Rollup all 100% (Complete) Summary Tasks Macro RRS feed

  • Question

  • Has anyone come up with an automated way of rolling up all complete tasks? At the moment I cant think of an easy way to do this yet.
    Thursday, December 19, 2019 4:30 AM

All replies

  • Have you tried a filter?
    Thursday, December 19, 2019 6:03 AM
  • At the moment I use:

    Status does not equal complete;

    OR summary equals Yes;

    And Status equals Complete.

    I wonder if anyone's figured out a macro to roll up summary tasks?

    Thursday, December 19, 2019 10:39 PM
  • luap88,

    Can you expand on this a little, perhaps with an example. I don't quite understand what you're asking. If all subtasks are complete (100%), the respective summary line (i.e. rollup) should also show 100%. I must be missing something.

    John

    Thursday, December 19, 2019 10:56 PM