  • How to track deleted and changed tasks in Project Professional?

    OR is there a way to track the same when Project Professional is connected to Project Server??


    Thanks, Siskin.

    Tuesday, June 3, 2014 9:58 AM

Answers

  • Hi Siskin,

    Unfortunately, unless you develop custom code to log transactions in Project Pro (and Pwa in the project plan), there is no out of the box feature to track tasks' updates.

    The baseline feature can give you a limited (11) number of snapshots you can compare your current project plan to.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by Siskin82 Wednesday, June 4, 2014 9:32 AM
    Tuesday, June 3, 2014 11:13 AM
    Moderator

All replies

  • Hi Siskin,

    Unfortunately, unless you develop custom code to log transactions in Project Pro (and Pwa in the project plan), there is no out of the box feature to track tasks' updates.

    The baseline feature can give you a limited (11) number of snapshots you can compare your current project plan to.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by Siskin82 Wednesday, June 4, 2014 9:32 AM
    Tuesday, June 3, 2014 11:13 AM
    Moderator
  • Siskin82,

    You might want to take a look at the Compare Project utility found in the Reports group. It will give you a report of changes between a Project file before changes and after changes.

    John