MS Project Professional RRS feed

  • Question

  • Hi Team,

    I am trying to export data from MS Project professional to excel.

    The baseline duration fields do not show up in the mapping, while baseline cost fields are getting exported.

    Please share your thoughts on how to export baseline duration fields to excel.

    Thanks in advance!

    Roshni.

    Thursday, November 29, 2018 7:24 AM

All replies

  • Hi Roshni,

    I don't see any problem while exporting to Excel. I can see all the Fields properly. may I know which version of MS Project are you using? I tested it on MPP 2016.

    Thursday, November 29, 2018 8:47 AM
  • Thanks for your reply!

    I am using MS Project 2013. 

    When I try to export normally to excel I can see the all fields, but the baseline duration fields do not come up while trying to export as Visual reports. Is it possible? 

    Thanks,

    Roshni.

    Thursday, November 29, 2018 10:56 AM
  • Roshni S --

    Duration-related fields are only available for Task Summary and Task Usage reports.  That is because all of the Duration-related fields, such as Duration and Baseline Duration, are Task fields.  Because they are Task fields, you can only use them in Task reports.  Out of curiosity, what type of Visual Report were you trying to add the Baseline Duration field to?  Please let us know and we will try to help you.


    Dale A. Howard [MVP]

    Thursday, November 29, 2018 9:12 PM