Mapping custom fields from Sharepoint to Project Professional and Visa Versa RRS feed

  • Question

  • Hi

    I hope someone can help

    I have a custom field in a sharepoint task list. I have been trying to find a way to map this field with the underlying MS project plan so I can use the information in a report. However, I cannot find a way to map custom fields between sharepoint or project no matter which software I create the field in

    Does anyone know if this is possible?

    Thanks

    Matt

    Thursday, June 21, 2018 1:19 PM

Answers

  • Hi Paul

    Thanks for getting back to me.

    I already use MSP Online, however I have a couple of sharepoint task lists set up so team members without MSP can  update non project plans.

    If they cannot be synced I will have to create a calculated field in both formats so the team can see it via sharepoint and it can be pulled into my BI report through project

    Thanks

    Matt

    • Marked as answer by Matt22365 Wednesday, August 1, 2018 1:31 PM
    Friday, June 22, 2018 6:53 AM

All replies

  • Hi Matt,

    This is a Microsoft sync process that can't be updated / edited. I think you would have to build your own sync process / function in MS Project. Have you considered Project Online?

    Paul


    Paul Mather | Twitter | http://pwmather.wordpress.com | CPS | MVP | Downloads

    Thursday, June 21, 2018 9:40 PM
    Moderator
  • Hi Paul

    Thanks for getting back to me.

    I already use MSP Online, however I have a couple of sharepoint task lists set up so team members without MSP can  update non project plans.

    If they cannot be synced I will have to create a calculated field in both formats so the team can see it via sharepoint and it can be pulled into my BI report through project

    Thanks

    Matt

    • Marked as answer by Matt22365 Wednesday, August 1, 2018 1:31 PM