how show start and finish for Split bars in Microsoft project RRS feed

  • Question

  • hi

    how can i find or show start and finish date for Split bars (one or more than once split) in Microsoft project?

    with formula or vba or etc ...

    thank you


    • Edited by payamof Sunday, December 27, 2020 2:19 PM
    Sunday, December 27, 2020 2:17 PM

All replies

  • payamof,

    The dates of some splits that result from out-of-sequence progress updating are shown by the task Stop and Resume fields.  In general, however, these dates are properties of the individual SplitParts of the task, which are only accessible through vba or other code.  The two dates in your example can be printed (in the Immediate window) using the commands:

    print activeproject.tasks("task1").SplitParts(1).Finish
    and

    print activeproject.tasks("task1").SplitParts(2).Start

    You could use similar statements to write these values into task custom fields.  

    Be careful.  SplitParts task collections often grow or shrink as the result of progress updating or resource leveling, and your code will need to be able to handle this.  Good luck, tom

      

    Sunday, December 27, 2020 8:50 PM