Non-Project Task Creation and Assignment RRS feed

  • Question

  • Hi,

      Is it possible for a "Manager" to create non-project tasks in Project Server 2010 (PWA / Professional) and assign it to his members.? I know about the "Administrative Tasks" , which is mainly the team member point of view. Whereas , in my case, manager should create some tasks which are not part of the listed projects and assign it to his team members.

    Thanks in advance.

    Regards

    Palani

    Thursday, April 18, 2013 6:36 AM

Answers

  • HiPalani --
     
    Nope, what your manage would like to do cannot be done in Project Server 2010.  Other than Administrative tasks, every other task must be part of an enterprise project.  Hope this helps.
     

    Dale A. Howard [MVP]

    • Marked as answer by HiPalani Thursday, April 18, 2013 1:14 PM
    Thursday, April 18, 2013 12:05 PM
    Moderator

All replies

  • HiPalani --
     
    Nope, what your manage would like to do cannot be done in Project Server 2010.  Other than Administrative tasks, every other task must be part of an enterprise project.  Hope this helps.
     

    Dale A. Howard [MVP]

    • Marked as answer by HiPalani Thursday, April 18, 2013 1:14 PM
    Thursday, April 18, 2013 12:05 PM
    Moderator
  • Thank you very much Dale.

    Regards

    Palani

    Thursday, April 18, 2013 1:16 PM
  • HiPalani --
     
    You are more than welcome for the help, my friend!
     

    Dale A. Howard [MVP]

    Thursday, April 18, 2013 1:25 PM
    Moderator