"An error occurred when communicating with the server. Check connectivity with your administrator to determine whether further action is necessary", then attempt to approve TimeSheet. RRS feed

  • Question

  • Kind day, colleague.

    It was required to organize a statement chain for TimeSheet of employees, as we realized. Everything is good, but at linear managers in PSW opportunity to execute Approve when viewing TimeSheet of the employee remained, and in attempt to approve TimeSheet there is a mistake.

    500 Internal Server Error

    "An error occurred when communicating with the server.  Check connectivity with your administrator to determine whether further action is necessary. "

    Accept, is carried out as it is necessary.

    It is a bug or we not correctly realized approval chain?
    Friday, January 31, 2014 6:46 AM

All replies

  •  issue is  related to the user booking time against a task that was past the finish/end date listed in the Project Schedule.

    To resolve the user needs to submit their time on a valid task that is still within the current reporting timeframe, or have the Project Manager update the task in questions so that the finish/end dates are at or beyond the submission period and then republish the project. After that, the user should be able to go in and submit their timesheet with success.

    http://patrickdrews.com/2012/09/project-server-2010-timesheet-submission-produces-an-error-occurred-while-communicating-with-the-server/


    kirtesh


    Friday, January 31, 2014 7:39 AM
  • Everyone keeps referencing this PatrickDrews article but that's not it.  Even submitting an empty timesheet, with no time entered, some users get this error.  We've deleted the timesheets and re-created, but still nothing.
    Tuesday, May 27, 2014 5:28 PM