Equipment Delivery as a Resource RRS feed

  • Question

  • So I am working a project that is highly dependent upon a piece of equipment being delivered on a given date.  Once that equipment arrives, we've got conflicting needs for it and I would like to be able to resource load the equipment, but make all the tasks dependent on it's delivery to us.  Is there something that I an do to make this happen.  I am running project 2007, but am willing to upgrade if this is a feature that was added later on.
    Friday, April 5, 2013 2:47 PM

All replies

  • NEOHMatt,

    Yes, I would set up a delivery milestone for the piece of equipment. Then link all tasks that will use that equipment in a normal finish-to-start relationship. Also create a resource for that piece and assign it as necessary to each task.

    John