  • Hi,

    I have a problem when creating a template in MSP 2010, I have the August 2011 CU.

    After creating and saving the template I apply it to the EPT. From there I create a new project and the inactive tasks become active.

    I have tried this on an environment with June 2012 CU and I can't replicate the problem.

    Am I right in assuming there has been a patch/hotfix that fixes this problem?

    Thanks

    Will 

    Wednesday, August 15, 2012 10:41 AM

All replies

  • Hello Will

    Can you check if this hotfix has been applied ? since you have June 2012 CU applied not sure if this is part of it you might want to check, but this hotfix included fixes to templates & seems to be correcting the issue

    http://support.microsoft.com/kb/2596498


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com

    Wednesday, August 15, 2012 2:27 PM